Commercial Backup Power
Commercial backup power is a generator or battery, an automatic transfer switch, and a fuel supply sized to keep a facility’s critical loads running through an outage. Grandview Contractors coordinates these systems for clinics, server rooms, cold storage, and multifamily buildings across Utah County and Salt Lake County — we hold the contract under our B100 license and manage licensed electricians, gas fitters, and generator technicians from load study through load test.

Commercial backup power versus a standby generator or a battery
The difference is what the system is obligated to carry. A residential standby generator protects comfort and a freezer. A commercial system protects something a code, a lease, a regulator, or an insurer cares about: egress lighting, a fire alarm panel, an elevator, a server room, refrigerated inventory, or a sump keeping a parking level dry.
Current Utah-adopted code sorts backup systems into three classes — emergency systems for life safety, legally required standby, and optional standby — each with its own rules for transfer time, wiring separation, fuel supply, and testing. Emergency loads must be back on within 10 seconds, and the fire marshal will time it. Classification is the first decision, because it drives conduit routing and how many transfer switches you need.
If you need one circuit of resilience rather than a facility-grade system, a transfer switch on an existing generator or a battery energy storage system may fit better. If you’re already planning a commercial electrical fit-out, backup power folds into the same permit package and trade schedule.
Load class, fuel, and switching: the three decisions that size the system
Load study first. A metered or calculated load study splits the facility into emergency, legally required, and optional loads. Life-safety circuits get their own panelboard and transfer switch, which is far cheaper to do while the tenant improvement walls are open than after a failed final.
Fuel. Natural-gas units run as long as the utility main does and need no on-site storage. Diesel delivers more kilowatts per footprint without depending on the gas main, but needs a belly or day tank, spill containment, and winter-blended fuel or tank heaters for January in Lehi. Diesel engines on the Wasatch Front may also need Utah Division of Air Quality review alongside the building permit; we raise that in the first meeting. Either way, output derates with elevation — at 4,500 feet a sea-level nameplate delivers less.
Switching. Automatic transfer switches are specified by amperage, transition type (open, closed, or delayed), and withstand rating against available fault current. Larger facilities run one switch per load class plus a load-bank connection so the unit is exercised under real load each year. Where a commercial EV charging array exists, chargers are shed first; we design that logic in.
The gas line extension, concrete pad, and sound-attenuated enclosure run under the same contract. A 6,000-pound generator near the Wasatch fault needs engineered seismic hold-downs, and the inspector will look for them.

How a commercial backup power installation runs
- Classify and size. Load study, load-class split, run-time target, and fuel decision, documented so the engineer and the city are reading the same sheet.
- Engineer and permit. Stamped electrical and structural drawings, the gas or fuel-system permit, and any air-quality review. Provo and Salt Lake City run established reviews; Saratoga Springs and Eagle Mountain can queue differently, and the schedule reflects the real timeline.
- Site and structure. Pad poured with an air-entrained mix for the freeze-thaw season, conduit and gas trenched, clearances set for exhaust, service access, and property-line noise.
- Set and connect. Crane day, anchorage, feeders, transfer switches, remote annunciator, and shed-load controls — each trade’s work checked by us before the inspector arrives.
- Test and hand over. Utility-fail simulation, transfer timing, a load-bank test to rated output, and a logged commissioning report with the maintenance schedule your insurer will ask for.
This runs under our MEP & systems coordination discipline, part of the renovation and build-out family. Our license, and every trade partner’s, is verifiable at dopl.utah.gov.

What does commercial backup power cost in Utah County?
As a ballpark planning number, a natural-gas system in the 50–150 kW range with one automatic transfer switch, pad, gas line, and commissioning typically lands between $60,000 and $180,000 installed along the Wasatch Front; diesel units with fuel storage and multi-switch emergency systems run higher. These are planning ranges, not quotes. What moves the number most:
- Load class. A true emergency system needs separate panels, separate raceways, and sometimes a fire-rated feeder route — more switches, more conduit, more inspection.
- Fuel type and storage. Diesel tanks, containment, and air-quality review add cost; a long run to the gas main or a meter upgrade adds it on the gas side.
- Site conditions. Crane access, an engineered pad on expansive clay, sound attenuation near neighbors, and seismic anchorage all show up as line items.
We price it as a defined scope after the load study — consultation, budget range, estimate, then proposal. FEMA’s guidance on emergency power is a useful read when deciding how much run-time to buy.
Questions we actually get
Does my building legally need backup power?
Some do. Assembly spaces, high-rises, buildings with elevators used for egress, and some healthcare occupancies carry emergency or legally required standby requirements under current Utah-adopted code; a retail or office tenant usually does not. Occupancy and city decide it, so we confirm with the building department and fire marshal before anyone sizes equipment.
Natural gas or diesel for a commercial generator in Utah?
Natural gas, when the main has the capacity and pressure — no tank, no fuel aging, simpler permitting. Diesel wins where the load is large, gas service is weak, or the owner wants independence from the gas utility after a seismic event. Diesel adds fuel storage, winter fuel management, and possible air-quality review, which we scope up front.
Do you install the generator yourselves?
No. Utah requires the electrical and gas work to be performed by licensed specialty contractors, and the manufacturer’s authorized technician commissions the unit. Grandview holds the contract, manages those licensed partners, sequences pad, trenching, crane, and connections, and quality-checks each stage before inspection.
Can backup power be added to an occupied building without shutting it down?
Mostly. The pad, gas line, enclosure, and transfer-switch rough-in happen with the building live. The final tie-in almost always needs a planned shutdown, usually a few hours after-hours, with temporary power for anything that cannot go dark. We schedule it with you and the utility weeks ahead.