Apartment unit turns & make-ready services
An apartment unit turn is the between-tenant reset on a single unit: repairs, repaint, flooring, fixtures, and cleaning to a fixed rent-ready standard, in days rather than weeks. Grandview turns apartment units for property managers and multifamily owners across Salt Lake County and Utah County under a B100 general contractor license.
When a standard turn is the right call
A unit turn is for an apartment coming back in roughly the condition it went out: normal wear, a few holes, scuffed walls, tired carpet, crusted fixtures. The goal is to re-rent it at the same market position, fast. If the unit is being pushed up a rent tier with new cabinets, counters, and lighting, that’s a value-add unit renovation; across dozens of units on a rolling schedule, it’s a bulk unit renovation program.
Turns stop at the unit door. Hallways, laundry rooms, and lobbies belong to amenity and common-area renovation, which runs on a building calendar, not a move-out calendar. The agreement that puts turns on a rate card is our unit turn program page.

What a make-ready apartment unit actually includes
“Rent-ready” means different things to different managers, so we write yours down first: paint colors and sheens by surface, flooring spec by room, the fixture list, and what the final clean has to pass. Then the crew is checking boxes, not making judgment calls.
Walls, ceilings, and doors
Drywall patching for nail holes, anchor pulls, and the doorknob dent behind every bedroom door. Then paint, where the real decision is touch-up versus full wall. Utah’s elevation and UV intensity fade paint on south- and west-facing window walls faster than most managers expect, so a two-year-old touch-up color rarely matches. We flag those walls for a corner-to-corner repaint instead of a patchwork that shows in listing photos; sheens and prep are on our interior painting page.
Floors
Carpet gets cleaned, stretched, or replaced with new pad; worn living-area carpet is increasingly swapped for luxury vinyl plank, which survives the next three turns. We check the subfloor while it’s exposed.
Kitchen and bath
Re-caulk tubs, showers, and counter seams; regrout where failed; swap aerators, shower cartridges, toilet fill valves, and supply lines. Wasatch Front hard water scales these parts fast, and a crusted aerator is the difference between a unit that feels clean and one that feels used. Appliances are swapped where the move-out inspection called for it.
Hardware, safety, and handback
Re-key, new blinds where the old ones are sun-cracked, smoke and carbon monoxide alarm test, thermostat check, then the final clean last so nobody tracks drywall dust across a shampooed carpet. On buildings built before 1978, work that disturbs painted surfaces follows the EPA Renovation, Repair and Painting rule — worth knowing if your portfolio includes older Salt Lake City stock.

How a single unit turns in five working days
A standard turn with full repaint, one room of new flooring, and fixture replacement runs five to seven working days from keys-back to listing photos; a light turn finishes in two or three.
- Keys-back walk. We compare the unit to the move-out inspection, photograph conditions, and confirm scope. A soft subfloor under the fridge gets priced on day one, not discovered on day four.
- Repairs and drywall. Patch, texture, prime, and door and cabinet adjustments while the unit is still dusty.
- Paint. Ceilings where in scope, then walls, then trim and doors. One crew, one color schedule.
- Flooring. Carpet or plank goes in after paint, so there’s nothing to protect and no touch-up at the base.
- Fixtures and plumbing trim. Where a turn uncovers more than fixture-level work — a water heater at end of life, a breaker that won’t hold — Grandview holds the contract and manages licensed plumbers and electricians inside the same schedule.
- Final clean and handback. Deep clean, carpet shampoo, filter change, heat set to a safe winter minimum, water checked, completion photos and a line-item record the same day.
In occupied buildings this happens behind a closed unit door, dust contained at the threshold and corridor floors protected. In the Provo–Orem student-housing cycle, where a building hands back dozens of units in one August week, the sequence runs in parallel with a crew lead per floor.
What does an apartment unit turn cost in Utah?
As ballpark planning numbers for Salt Lake County and Utah County, not quotes: a light turn on a one-bedroom — patch, touch-up, caulk, fixture trim, clean — commonly lands between $1,000 and $2,500. A standard turn with full repaint, new flooring in one or two rooms, and fixture replacement typically runs $3,500 to $8,000.
- Bedroom count. A three-bedroom turn is close to double a studio.
- Touch-up versus full repaint. Sun-faded walls, dark accent colors, and smoke residue push a unit to full repaint.
- Flooring material. Carpet-and-pad is the lowest per-turn cost; plank costs more once and less over the next several turns.
Our license is verifiable at dopl.utah.gov. For the small jobs between turns — a drywall patch after a move-in — on-call property maintenance covers the gap.

Questions we actually get
Can you turn a single apartment unit, or only whole portfolios?
Both. A single unit prices as its own small project; a steady flow of turns prices from a rate card under a unit turn program. Same standard either way; the program removes the bidding step and holds crews and materials for you.
Why can’t you just touch up the walls instead of repainting?
Often we can, and we’ll say so. Touch-up fails when the paint has faded, the sheen or batch doesn’t match, or a tenant painted an accent color. Utah’s sun fades window walls quickly, and a wall that flashes in the listing photos costs more in days on market than the repaint.
What happens if you find damage during the turn?
We stop at that boundary, photograph it, and send you a priced scope the same day. The rest of the turn keeps moving wherever the discovery doesn’t block it. Active leaks or electrical hazards get stabilized first and papered second. Nothing outside the agreed scope reaches the invoice unannounced.
How much does a full repaint and new flooring add to turn time?
A full repaint adds roughly two days over touch-up on a typical two-bedroom; new plank or carpet in one or two rooms adds about a day, after paint. Together they push a turn from two or three working days to five to seven, so scope should be decided before keys come back.
Tell us what you’re working on
Send us the unit, the move-out date, and your rent-ready standard if you have one. We reply within a couple of hours during business hours, a day at most, with a straight read on scope, days, and cost. Part of our repair, restoration & property services family.